Currently when we create line list query in Plantsight and include TO/FROM fields, it shows multiple values in both fields, there should be a way to show only start and end point of pipelines, intermediate runs shouldn't be reported in the TO/FROM fields.
| How frequently will feature be used? | A few times a week |
| How much time will you save? | It will save a lot of time for our Process team, currently they have to remove the extra values manually. |
| Your Industry | Mining |
Most of the development work is completed for this enhancement and we plan to deliver this in the next minor release of OpenPlant PID 2026.01.
We have clarified the requirements of this item and will be discussing where we can fit this feature into our roadmap.